Curtain Wall Architecture Construction Project Schedule
In order to optimize the SlenderWall system, it is highly recommended
that Easi-Set be involved in the coordination of details, connections
and panelization options early during the design development phase. Because
plant availability may vary, it is best to award the SlenderWall façade
contract prior to other trades. This will also facilitate incorporation of
SlenderWall connections into the Contract Documents. The timeline below
represents a typical project schedule, incorporating SlenderWall into
the subcontract. Note that the timeline below depicts representative durations
to achieve maximum economy. Depending upon project complexity, these durations
may vary. Allowing for optimal lead times and production rates will help
keep costs low and quality high. Easi-Set can assist you in preparing
a more detailed schedule for each project to integrate into the overall project
timeline.

| Prepare Contract Drawings |
|
|
|
|
| |
Contract Awarded 50% Contract Drawing
Completed |
| |
Start Shop Drawings 3 weeks after Contract Awarded |
| |
Start Production 12 weeks after start of shop drawings |
| |
|
Start Delivery Duration negotiated prior to contract signing.
Minimum 80% produced.
|