Exterior Wall Panel Penetrations
Penetrations through the precast that may be required for wall hydrants,
pipe penetrations and light fixtures can be cast into the panels provided
the coordination for location and size is done early enough in the shop drawing
development. Ideally, the location and size of these penetrations should
be provided to Easi-Set designers about 8 weeks prior to fabrication.
This is to ensure that the information can be incorporated into the shop
drawings and fabrication drawings in adequate time. For openings less than
10-inches square, it is recommended that the penetrations be field cut. However,
in no instance should the heavy-gauge stud frame be cut.